How to write a running order that survives late changes (free template)

Ben Wratten
By Ben Wratten · Co-Founder, Stage Portal
23-November-2026

Every running order is right at 7am. The question is whether it's still right at 11. This is how we build running orders for conferences and summits so they keep working when the day changes, plus the template we use.
We've had hosts and speakers change at the last minute more often than we'd like. A flight is cancelled. A train doesn't run. Someone's unwell. On a summit with international speakers, at least one person's plans will move.


None of that has to be a crisis. What turns it into one is a running order that only works if everything goes to plan: no slack, no cover, and five different versions in five different hands.


A good running order isn't the most detailed one. It's the one that can take a change at 10am and still be the version everyone is working from at 10:05.


[Download the free running order template] (button link to the template landing page)


If you're planning the whole event, start with our corporate event planning checklist. The running order is one part of it.

What goes in a running order

Keep it to the columns people actually read on the day. Ours has these:

Column

What goes in it

Who reads it

Cue

A line number, so people can say "we're on 14" over the radio

Everyone

Start and end

Worked out from the start time and each line's duration

Everyone

Mins

How long the line runs. This is the only time you type

Event director

Item

What's happening, in plain words

Everyone

On stage

The host, speaker or panel

Stage manager, host

Cover

Who steps in if they can't

Event director, stage manager

AV (sound and lighting)

Mic changes, walk-up music, lighting states

Sound and lighting

Video and slides

Which deck and version, videos with sound, holding slides

Video operator

Notes

Anything else the line needs

Everyone

Type

Session, changeover, break, buffer or cut point

Event director

 

Two columns do most of the work when things change.

Mins, not times. Type the start time once, then a duration for each line. Every start time is the previous line's end. When a session runs five minutes over, you change one number and the rest of the day moves with it. If you type every time by hand, one change means retyping the day, and someone will miss a line.


AV and video split out. Sound and lighting cues go in one column, video and slides in another, because they're usually different people. The sound engineer shouldn't have to read past the slide notes to find their mic change, and the video operator needs to know which version of the deck to load, not just which speaker is on.

Build the time in before the day

Most overruns can't be prevented. What you can control is where the time comes back from.


Bank your speakers
Don't mic up each speaker as they walk on. In the break before a session, mic up the next three or four speakers and run them back to back, with a one-minute changeover between each. On a bigger production, keep a tech team side of stage with the next speaker already mic'd and waiting.


It does two things. Changeovers drop from five minutes to one, and if a mic has a problem, you find out in the break, not in front of the room.


Put your buffers where you can use them
Don't scatter five spare minutes across every session; they get eaten and nobody notices. Put the slack where you can take it back:

  • The round-up and closing notes. A 10-minute round-up can become three without anyone in the room knowing.
  • The breaks. A 30-minute break can lose five minutes if the next session starts on time.


Mark these lines as Buffer in the running order, so the event director can see at a glance where the time is.

 

Decide your cut points now
When you're 15 minutes behind at 11am, it's too late to decide what goes. Decide the day before, and mark it as a Cut point:

  • Panel Q&A, from 10 minutes to five
  • A video that can be dropped

If everyone already knows the cut points, the event director can make the call in one sentence, and the relay can tell AV before the host has finished speaking.


Name a cover for every host and speaker
Hosts and speakers change at the last minute. Travel is the usual reason. So every host and speaker line in our running order has a Cover column: the person who steps in if they can't.


The cover needs more than their name on a sheet. Brief them as if they're on: their slot, their mic, the deck, and what to say if they're stepping in at short notice.

The four rules for handling changes on the day

The running order will change. These four rules keep everyone on the same version when it does.


1. One person owns the changes
On the day, only the event director changes the running order. The host doesn't, the speaker doesn't, and AV doesn't. Everyone else asks.
It sounds strict. It's the only way to know the version in your hand is the real one.


2. One person tells everyone
The event director decides; a dedicated relay tells. The relay's job is to take each change to AV, the stage manager, the host and any speakers it affects, and confirm they've got it.


Splitting the two jobs matters. The event director's attention stays on the room, and nobody hears about a change second-hand from a colleague who half-remembered it.


3. Every copy carries a version
Every time the running order changes, update the version and the time it was issued, and print them on every copy: v4 · 10:42. If two people are holding different sheets, the higher version wins, with no discussion.


4. Every change goes in the log
One line per change: what changed, why, and who was told. It takes ten seconds, and it does three jobs. It's the relay's checklist, it settles any "nobody told me" afterwards, and it's the first draft of your event report.

Key Takeaways

  • Type durations, not times, so one change moves the whole day.
  • Bank your speakers: mic up the next three or four in the break.
  • Put your buffers in the round-up, closing notes and breaks, and decide your cut points the day before.
  • Name a cover for every host and speaker, and brief them as if they're on.
  • One person owns changes, one person relays them, every copy has a version, and every change is logged.

Get the template

Our running order template has all of this built in: start and end times that update when you change a duration, AV and video columns, a cover for every line, buffer and cut point highlighting, a mic and speaker plan for banking speakers, and a change log. It works in Excel and Google Sheets.

[Download the free running order template] 

Run it without the spreadsheet

A spreadsheet still relies on someone printing the latest version and handing it round. Stage Portal keeps one running order your team, venue, speakers and crew all work from, so when the event director makes a change, everyone sees it at the same time.


[Book a demo]

Questions

What is a running order?
A running order (also called a run of show) is the minute-by-minute plan for an event: what happens when, who's on stage, and what sound, lighting and video need to do at each point. It's the document the event director, stage manager, host and AV team all work from on the day.

 

What should a conference running order include?
At minimum: a cue number, start and end times, duration, what's happening, who's on stage, a named cover, sound and lighting cues, video and slide notes, and whether each line is a session, changeover, break, buffer or cut point.

 

How much buffer should you build into a running order?
Put it where you can take it back, rather than spreading a few minutes across every session. The round-up, closing notes and breaks are the usual places, along with cut points you've agreed in advance, such as shortening Q&A.

 

Who should be allowed to change the running order on the day?
One person: usually the event director. A second person relays each change to AV, the stage manager, the host and speakers. Every copy carries a version number and issue time, so everyone knows which one is current.

 

What's the difference between a running order and a run sheet?
The terms are often used interchangeably. Some teams use "running order" for the timed programme and "run sheet" for the fuller document with crew calls and logistics. The template covers both on one sheet.

The Advance Podcast

Short episodes. Real insights.

The Advance is a podcast for independent artists and band managers. Each episode covers one practical topics for improving gig logistics.

The Advance

One email a week on running live events

Guides, product news and one thing to try before your next event.

We'll only email you The Advance. Privacy policy

Cookie Settings

We use cookies to improve your experience

We use strictly necessary cookies to keep the site running. With your permission we'd also like to use others to help us to improve your experience by providing insights into how the site is being used

Strictly Necessary

Required for the site to function. Cannot be disabled.

Analytics

Analytical cookies help us to improve our website by collecting and reporting information on its usage.

Marketing

We use marketing cookies to help us improve the relevancy of advertising campaigns you receive.

Read our Privacy Policy for more information.